Day 48: To further construction
Today there is some information without photos. After the appointment with the construction manager are now further down the building steps.
from 10-12.08.2009 the drywall trowel
from 11-13.08.2009 the fine installation of sanitary facilities
made on Thursday, 13/08/2009 is our staircase - I'm already looking forward to something and hope that it looks exactly as we imagine.
on 14.08.2009, the pre-acceptance - after a week we have for painting available
and on time on Aug 27, 2009 will then be the house delivery. It runs so everything as planned. For this purpose, again a big congratulations to the Bauunion 1905. The organization of the individual steps is really balanced almost perfectly. Thank you.
In the meantime, the hallway and the guest bathroom was tiled including joints finished. Just fill in the gaps in the utility room and the bathroom completely, the floor tiles. The window sills were installed and we are now connected to electricity and water.
More photos and details to follow again next time until then.