Saturday, August 28, 2010
Experiment With Guppy Fish And Water Plants
... is evident in our house plan.
The last days were finally re-marked by progress. Has started the whole thing with our first site manager interview. Known by her own experiences were full of praise for our site manager of Mr. Gericke Construction Magdeburg. We can only confirm. This also increases the hope that it works better now than before.
The second important event is the issuance of building permit by the Building Authority - a few days before the deadline we received this positive message. Apparently our friendly insistence helped.
order to begin the construction work is missing, more than a confirmation of the Land Registry on the registration of the mortgage. It's not as if this was mandated by our notary almost 2 months, but apparently the mills grind on this special authority particularly laannnggggsaaaammmmm. My colleague told me that his house already stood as the necessary documents were finally ready. Alternatively, we can still rely on a notarized - but unfortunately costs a few hundred euros.
Now we are very excited about how and when the first observable during the actual construction activities are identified.
Tuesday, August 17, 2010
How To Make Backpack Goodie Bags
Overwhelmed?
In my last post, after all, been almost 3 weeks since I had already missed so to test statics. The status has unfortunately not really changed - it is still not finished. On the part of the construction company owned architectural firms have tried to justify this. But really believable and understandable, especially these attempts were not. Apparently, there are currently some problems to work out the orders.
few days ago I had a revealing conversation with the sales activist. She explained that we unfortunately are the only ones affected by such problems and delays. Even in our drainage problem they had some information that can FIBAV not really look good. It confirmed our descriptions regarding the events prior to the signing again - and thus contradicted the statements of the contractor.
In my last post, after all, been almost 3 weeks since I had already missed so to test statics. The status has unfortunately not really changed - it is still not finished. On the part of the construction company owned architectural firms have tried to justify this. But really believable and understandable, especially these attempts were not. Apparently, there are currently some problems to work out the orders.
few days ago I had a revealing conversation with the sales activist. She explained that we unfortunately are the only ones affected by such problems and delays. Even in our drainage problem they had some information that can FIBAV not really look good. It confirmed our descriptions regarding the events prior to the signing again - and thus contradicted the statements of the contractor.