Friday, August 7, 2009

Put Your Head On A Hairstyle?

Day 48: To further construction

Today there is some information without photos. After the appointment with the construction manager are now further down the building steps.

from 10-12.08.2009 the drywall trowel
from 11-13.08.2009 the fine installation of sanitary facilities

made on Thursday, 13/08/2009 is our staircase - I'm already looking forward to something and hope that it looks exactly as we imagine.

on 14.08.2009, the pre-acceptance - after a week we have for painting available

and on time on Aug 27, 2009 will then be the house delivery. It runs so everything as planned. For this purpose, again a big congratulations to the Bauunion 1905. The organization of the individual steps is really balanced almost perfectly. Thank you.

In the meantime, the hallway and the guest bathroom was tiled including joints finished. Just fill in the gaps in the utility room and the bathroom completely, the floor tiles. The window sills were installed and we are now connected to electricity and water.

More photos and details to follow again next time until then.

Tuesday, August 4, 2009

Track Previous Bond Prices

Day 45: Self-service tile go

The holiday is our construction company is now over. But before it really goes, we must first make the rest of the internal activities of the tiles done. That is, we must lay the floor tiles.

done Said. Today we have tiled the guest bathroom, sorry no picture, the utility room and the hallway. Tomorrow, then the rest made ready. The joints have to be made even more so that it does not collect the dirt.

was the way the supply air for the chimney exposed and laid out in a shaft. The public utilities have freigebuddelt the drinking water and electric aufgeruppt ditch and the road for sewage. In addition, "very secret" range makes the nets at the ground-level windows in the floor. The lack of joints in two terrace windows were installed.

Tomorrow is a meeting with the supervisor, where we will discuss the rest of everything else and vote. This then more tomorrow.

Saturday, August 1, 2009

African Spurred Tortoise Breeder In Ontario

Day 42: garden and much, much more

was early morning around 9.00 clock today on this sunny Saturday on the site. The first external or gardening on stand. We wanted to remove the entire large weeds, clear away the rubble and garbage, dig the trench for sewage and in a manner few details.

But it's like always different than you thought. The soil on the plot is as hard as stone and had to remove the weeds is therefore no longer. Since you probably need a backhoe to dig up more. Thus we started the smaller Unkrautepflanzen removed and the high grass at least once before to reduce to the minimum height. Thus we were also employed for a while.

have made me the way I to the removal of the concrete remains on the property. Is very hard work. Tomorrow I have in any case, twice as many arm muscles as today. Nevertheless, it was great fun, after all, you do it so for his own home.

Our child was always there and has supported us. He has also made new friends immediately. Our neighbors have 2 Houses continue to visit us. Today in which the blower door test was done. They have a daughter who is as old as our son. This is super.



Then we dug the drainage ditch. My honorable task consisted in the
proper exposure of the tube.

And by the way, my Schatzi sealed nor the pan and, over the last week the bathroom tiles all over and jointed.

Finally, we have now removed our utility room, attached to the mail box and the first time grilled. It's pretty much happened today. And now, we will re-register us well soon and officially move into our new home. Wonderful.

Our immediate neighbors are beginning to build also. We are very happy for you and wish you well. We'll see if that also agrees with the storks always so ... ;-)

From next week it goes back further with Bauunion, will then have to pass your vacations.