Update As has happened in recent days, but good stuff "in construction", here's a quick update :
plastering showed the first decrease in the interior plaster, that a small rework are necessary. Fortunately, the frost seems to have taken no negative influence. The first attempt was to eliminate the deficiencies are not so very successfully, so it goes shortly into the second overtime. To be continued ...
Plumbing & Heating The last days were the employees of the company Rothermann hard to swing. The raw installation of heating and plumbing was at 07.02. completed. There were a few surprises that we did wonder. After we (actually mainly the better half of us two) had put it some effort into the bathroom planning and had this also voted diligently with the heating and plumbing company, there were two unexpected events:
The laying of the channels for our air conditioning was not as be planned, since it was installed in the floor, a steel support so that he was a few inches above the unfinished floor (still with vesehen screed) stood out.
The fixtures for the Bath could not be built as planned, as is the ring beam at this point.
What we ask ourselves: Those are really things that are visible in the drawings, why is that the skilled man of the heating and plumbing company noticed does not advance. Fortunately, the local staff able to assist us in solving the task. Ml look at what we now attempt to pass on extra costs to us.
Here again a few pictures:
|
| Fußbodenheizungsgeschlängel - in an interesting color |
|
| Part of the house connections |
|
| floor Stage 2: Land of the channels for the ventilation system |
|
| cross-section of the floor in level 2 |
|
The ventilation system (unfortunately I have a "problem" with the portrait - you just HAVE to times when viewing on its side) |
screed laid After the raw installation of heating and plumbing like the "floor layers" and are now ready to go now. In one week we can then set the first time a foot in our advanced construction.
electrical service entrance More of a tiresome subject: Apparently there are people in the neighborhood who have forgotten how their own house construction expired a few years ago. They took exception to the Baustromkästen, which were placed near the junction boxes. Admittedly not a pretty as before a plot of land, but temporary sight. There were several letters from the Government, which was ultimately with the threat of a misdemeanor its peak. So
Flux offset all into a frenzy and asked the utility to the activation of the electric service connection. Within 2 weeks ski screened two attempts because the application documents for the Stromvesorgung not arrived by post from us. One should sometimes the internal processes and the Postal Service under the microscope. And finally we got the documents he prefers it personally. Thanks to many calls, faxes and the support of some people made it the boss finally has, within 2 days of electricity in our house - but the Baustromkasten is now gone.
Further planning In the next few days (of course only if it allows the screed), we take our tilers. We want him to be "surprised" with our desires and our previous plans and hope in one way or another idea on his part.
After our construction manager has given us an updated construction schedule is available, we know it now: In early April to take place, the completion and handover to us.